Use Name, not a Text property. A task's caption is Name; its long
text is Description. Schedule fields are PlannedStart and PlannedDuration
(a duration object with Value and DurationType), not StartTime/Duration.
Always pair BeginUpdate/EndUpdate. Bulk task or option changes outside an
update block force a recalculation per change and can flicker. Use
try…finally so EndUpdate always runs.
Build before you configure columns. Configure columns and timeline against a
project that already has tasks, so auto-sizing and sorting have data to work with.
Durations and the decimal separator.Value is a Double. When loading
locale-sensitive data (e.g. CSV authored with .), align
FormatSettings.DecimalSeparator or fractional durations may parse wrong.
WorkTimePolicy migration. Older projects stored a UseWorkingHours
boolean. A stored False now maps to whAllTime; opening such a file may raise
an error you can safely ignore once you set the task's WorkTimePolicy
explicitly.
Unscheduled tasks. A task with no PlannedStart is treated as unscheduled
and only appears on the timeline when Appearance.Options.DrawUnscheduledTasks
is enabled.
Filtering needs the predefined property names.AddAND, Parse, and
Sort all use the identifiers taskname, progress, startdate, etc. — the
same names used for columns. A typo silently matches nothing.
Sorting is a one-time operation.Project.Sort reorders the tasks once; it
does not keep new or edited tasks sorted automatically. Re-sort after adding
tasks if you need a stable order.
A shared project is owned by whoever created it. When you assign your own
TTMSFNCGanttProject instance to several charts, manage its lifetime yourself;
the internal default project is owned by the chart and should not be freed.
Export columns are separate from screen columns.TaskListColumns on the
PDF/Print options does not inherit the on-screen task-list columns — configure
the exported columns explicitly or the export shows none.