Core concepts

A few terms recur throughout the Gantt Chart API. Understanding them up front makes the rest of the guides easier to follow.

  • Chart vs. project. TTMSFNCGanttChart renders and handles interaction; TTMSFNCGanttProject holds the tasks, states, and work-time calendar. Access the active project through TTMSFNCGanttChart.Project. You can assign a separate project instance to share one schedule between views.
  • Tasks and the WBS. Each TTMSFNCGanttTask has a Name, Description, PlannedStart, PlannedDuration, Progress (0–100), and Cost. Nesting tasks builds a work-breakdown structure; each task exposes a computed WBS string and a SubTasks collection. A summary task derives its dates from its children.
  • Durations and work-time policy. A duration carries a Value and a DurationType (gdtSeconds, gdtHours, gdtWorkDays). When a task uses gdtWorkDays, its WorkTimePolicy decides whether non-working days and hours are skipped (whWorkTimeAndDays), only non-working hours are skipped (whWorkTimeOnly), or time runs continuously (whAllTime).
  • Dependencies. A TTMSFNCGanttTaskDependency links two tasks with a type (gtdFinishToStart, gtdStartToStart, gtdFinishToFinish, gtdStartToFinish) and an optional delay. Dependency arrows are drawn automatically on the timeline.
  • States. A TTMSFNCGanttTaskState is a named, colored status with a priority level. States are reusable across tasks and can color the timeline bars.
  • Two panels. The control is split into a task list (configurable columns) on the left and a timeline (two-tier time header plus bars) on the right, separated by a draggable splitter.