Work-time calendar

When tasks are measured in working days (gdtWorkDays), the project's work-time calendar defines what "a working day" means. Configure the working weekdays, the working-hours span within a day, and any holidays; tasks that respect work time then skip weekends, off-hours, and holidays when their bars are laid out. This is what keeps a "3 working days" task from spilling across a weekend.

Configure the project work-time calendarPascalC++
procedure TForm1.ConfigureWorkTime;
var
  LSpan: TTMSFNCGanttTimeSpan;
  LHoliday: TTMSFNCGanttHoliday;
begin
  TMSFNCGanttChart1.BeginUpdate;
  try
    { Only these weekdays count toward gdtWorkDays durations. }
    TMSFNCGanttChart1.Project.WorkTime.WorkingDays :=
      [gdMonday, gdTuesday, gdWednesday, gdThursday, gdFriday];

    { Replace the default span with a 9-to-17 working day. }
    TMSFNCGanttChart1.Project.WorkTime.WorkingHours.Clear;
    LSpan := TMSFNCGanttChart1.Project.WorkTime.WorkingHours.Add;
    LSpan.StartTime := EncodeTime(9, 0, 0, 0);
    LSpan.EndTime := EncodeTime(17, 0, 0, 0);

    { Holidays are skipped for tasks that respect work time. }
    LHoliday := TMSFNCGanttChart1.Project.WorkTime.Holidays.Add;
    LHoliday.StartDate := EncodeDate(2026, 12, 25);
    LHoliday.EndDate := EncodeDate(2026, 12, 26);
  finally
    TMSFNCGanttChart1.EndUpdate;
  end;
end;
void __fastcall TForm1::ConfigureWorkTime()
{
  TTMSFNCGanttTimeSpan *LSpan;
  TTMSFNCGanttHoliday *LHoliday;

  TMSFNCGanttChart1->BeginUpdate();
  try
  {
    // Only these weekdays count toward gdtWorkDays durations.
    TMSFNCGanttChart1->Project->WorkTime->WorkingDays =
      TTMSFNCGanttDays() << gdMonday << gdTuesday << gdWednesday << gdThursday << gdFriday;

    // Replace the default span with a 9-to-17 working day.
    TMSFNCGanttChart1->Project->WorkTime->WorkingHours->Clear();
    LSpan = TMSFNCGanttChart1->Project->WorkTime->WorkingHours->Add();
    LSpan->StartTime = EncodeTime(9, 0, 0, 0);
    LSpan->EndTime = EncodeTime(17, 0, 0, 0);

    // Holidays are skipped for tasks that respect work time.
    LHoliday = TMSFNCGanttChart1->Project->WorkTime->Holidays->Add();
    LHoliday->StartDate = EncodeDate(2026, 12, 25);
    LHoliday->EndDate = EncodeDate(2026, 12, 26);
  }
  __finally
  {
    TMSFNCGanttChart1->EndUpdate();
  }
}
A task bar whose working span skips a holiday and the weekend A task bar whose working span skips a holiday and the weekend

What the calendar holds

Project.WorkTime groups three editable collections plus two computed values:

Member Purpose
WorkingDays A TTMSFNCGanttDays set of gdMonday…gdSunday marking which weekdays count.
WorkingHours A collection of time spans (StartTime/EndTime) describing the working portion of a day.
Holidays Date ranges (StartDate/EndDate) excluded from work time.
WorkDayStart / WorkDayEnd Read-only earliest/latest working times derived from WorkingHours.

Several working-hour spans are allowed in one day — for example a morning and an afternoon block around a lunch break.

Work-time policy per task

Each task chooses how strictly it follows the calendar through WorkTimePolicy:

  • whWorkTimeAndDays — skip both non-working days and non-working hours (default).
  • whWorkTimeOnly — skip non-working hours but run across every day.
  • whAllTime — ignore the calendar; duration is continuous wall-clock time.

Editing the calendar at runtime

To let users manage the calendar, the product ships modal editors: TTMSFNCGanttTimeSpanEditor edits a single working-hours span and TTMSFNCGanttHolidayEditor edits a holiday. Create one, assign its TimeSpan or Holiday, call Execute, and refresh your UI.

Note

WorkTimePolicy replaced the older UseWorkingHours boolean. Tasks saved with UseWorkingHours = False map to whAllTime; see Common pitfalls.

Putting it together

Configure the calendar, give a task a work-time policy, and add a holiday at runtime that reschedules dependent work:

Calendar, a per-task policy, and a runtime holiday editPascalC++
procedure TForm1.CalendarEndToEnd;
var
  LSpan: TTMSFNCGanttTimeSpan;
  LHoliday: TTMSFNCGanttHoliday;
  LTask: TTMSFNCGanttTask;
begin
  TMSFNCGanttChart1.BeginUpdate;
  try
    { What the calendar holds: working days and hours. }
    TMSFNCGanttChart1.Project.WorkTime.WorkingDays :=
      [gdMonday, gdTuesday, gdWednesday, gdThursday, gdFriday];
    TMSFNCGanttChart1.Project.WorkTime.WorkingHours.Clear;
    LSpan := TMSFNCGanttChart1.Project.WorkTime.WorkingHours.Add;
    LSpan.StartTime := EncodeTime(9, 0, 0, 0);
    LSpan.EndTime := EncodeTime(17, 0, 0, 0);

    { Work-time policy per task: this task respects working hours and days. }
    LTask := TMSFNCGanttChart1.Project.AddTask('Build', 'Implementation',
      Trunc(Now), 5, gdtWorkDays, whWorkTimeAndDays, 0);
    LTask.WorkTimePolicy := whWorkTimeAndDays;
  finally
    TMSFNCGanttChart1.EndUpdate;
  end;

  { Editing the calendar at runtime: a new holiday reschedules dependent work. }
  LHoliday := TMSFNCGanttChart1.Project.WorkTime.Holidays.Add;
  LHoliday.StartDate := EncodeDate(2026, 12, 25);
  LHoliday.EndDate := EncodeDate(2026, 12, 25);
end;
void __fastcall TForm1::CalendarEndToEnd()
{
  TTMSFNCGanttTimeSpan *LSpan;
  TTMSFNCGanttHoliday *LHoliday;
  TTMSFNCGanttTask *LTask;

  TMSFNCGanttChart1->BeginUpdate();
  try
  {
    // What the calendar holds: working days and hours.
    TMSFNCGanttChart1->Project->WorkTime->WorkingDays =
      TTMSFNCGanttDays() << gdMonday << gdTuesday << gdWednesday << gdThursday << gdFriday;
    TMSFNCGanttChart1->Project->WorkTime->WorkingHours->Clear();
    LSpan = TMSFNCGanttChart1->Project->WorkTime->WorkingHours->Add();
    LSpan->StartTime = EncodeTime(9, 0, 0, 0);
    LSpan->EndTime = EncodeTime(17, 0, 0, 0);

    // Work-time policy per task: this task respects working hours and days.
    LTask = TMSFNCGanttChart1->Project->AddTask("Build", "Implementation",
      Date(), 5, gdtWorkDays, whWorkTimeAndDays, 0);
    LTask->WorkTimePolicy = whWorkTimeAndDays;
  }
  __finally
  {
    TMSFNCGanttChart1->EndUpdate();
  }

  // Editing the calendar at runtime: a new holiday reschedules dependent work.
  LHoliday = TMSFNCGanttChart1->Project->WorkTime->Holidays->Add();
  LHoliday->StartDate = EncodeDate(2026, 12, 25);
  LHoliday->EndDate = EncodeDate(2026, 12, 25);
}

See also